Building Projects


October 3, 2016  Final Update on Renovation to Parish Center and Storage

Parish Center Project:

 

parish-center-north

 

parish-center-south

 

 

Expenditure on Parish Center and Parish Storage:  I am happy to update you all with the total amount of money spent. As of October 3, 2016, we have spent total amount of $231, 801.19 both on the Parish Center and on the Parish Storage.

Parish Center:  With this amount of money we able to put in new ceiling, new heat and air, 46 new glass windows, blinds, wooden flooring, carpeting, kitchen, two water fountains, painting, new cabinets, renovated the seven class rooms on the first floor taking away one closet on each room, created work room for catechists, added three bath room spaces on both the levels, new extended porch, new face lift on the front side of the building on east side, pressure wash the whole building, replaced the wood work in the exterior of the center.

Parish Storage:  Together with that we also renovated the existing garage making it official storage for the whole parish accommodating the parish organizations. We have created four separate spaces for the parish organizations and put in four different doors and one main door on the east entrance of the storage. We also put on a new roof on the garage, new ceiling, painting and power washed the facility.

All this was possible because of your generosity and support. Thank you to each of you who made this dream possible by your contributions. On the same note, we have finalized our Administrative building plans and would be presenting to you all very soon. Look for them. We are moving very well in the right direction and we would very much count on your generosity and support. Together we can make this administrative building plan realized very soon.

Thank for all that you are to Holy Trinity Parish. God bless you all abundantly.

Fr. John Peter

 

 

Garage/ Storage Project:

This is our official storage for the parish and its organizations. There are four separate spaces for the parish organizations with one main door on the east entrance of the building. The garage/storage facility had a new roof put on and the building was power washed .

 

 

 

 

 

Intended Use:

Holy Trinity School – two classrooms on the north end of the building

Religious Education – upstairs classrooms and workroom

Parent Association – storage space upstairs

Other uses for the building:  RCIA, New Evangelization Meetings, Money Counters, Parish Nursery Program, Adult Education Programs

Finally, the space near the kitchen (Lenore Robb suite) will be available to rent out for parishioners to use at a very low cost for small functions.

 

 

 


 

 

Building Project Pictures